- ClientMillers Recovery (Millers of Longton) Value
- Value£300,000
- Duration8 weeks
Our operations require respect for the land, water and broader environment in which we work. We continuously strive to mitigate any adverse impacts our essential business may have on the environment, and we prioritise the safety, health, wellbeing and governance of not only our employees, but also the communities in which we live and work.
Scope of Works
- Soil strip and dispose to tip for later re-use as restoration
- Cut and fill with disposal of surplus
- Installation of Geotextile and Geogrid
- Import clean recycled 6C
- Import recycled Type-3 MOT
- Lay permeable and non permeable asphalt
- Installation of drainage/oil interceptor















Northstone, Old Hall Road, Bromborough
Site Remediation
- Northstone
- £700k
- 22 Weeks
Our operations require respect for the land, water and broader environment in which we work. We continuously strive to mitigate any adverse impacts our essential business may have on the environment, and we prioritise the safety, health, wellbeing and governance of not only our employees, but also the communities in which we live and work. Scope of Works Site clearance
Northstone, Victoria Road, Horwich
Site Remediation
- Northstone
- £430k
- 14 Weeks
Our operations require respect for the land, water and broader environment in which we work. We continuously strive to mitigate any adverse impacts our essential business may have on the environment, and we prioritise the safety, health, wellbeing and governance of not only our employees, but also the communities in which we live and work. Scope of Works Site strip